Project Overview
Development of surface and subsurface facilities to support Eocene reservoir
production at the Wafra field, including wellhead facilities and gathering
systems, flowlines and manifolds, central processing and utility systems,
and integration with existing Wafra field infrastructure.
The tender (JO/HC169/PD25) has been issued and extended by the client and is
currently at bidding stage. Total duration is approximately 52 months:
2 months mobilization, 40 months construction, 12 months defects liability.
Brownfield integration with existing facilities, large-scale upstream
infrastructure, and multi-discipline engineering and execution make this a
strategically important development for Kuwait–Saudi joint production. VEE
is participating at tender stage, providing engineering, sourcing, and
proposed PMC capabilities and engaging with international OEMs and partners
for execution strategy.
Scope of Work
- Front-End Engineering Review and Detailed Engineering
- Wellhead and surface facility design
- Pipeline routing and stress analysis
- Process system design and integration
- HSE and environmental compliance design
Deliverables
- Procurement of oilfield equipment and materials
- Construction of well pads, flowlines, and processing facilities
- Mechanical, piping, electrical, and instrumentation works
- Testing, pre-commissioning, and commissioning
- Proposed PMC: planning, cost control, QA/QC, HSE, handover